MPI Adventure bei der Errichtung der Anlagen
40 AREVA M5000 Anlagen werden im Trianel Windpark Borkum (Phase 1) errichtet
Parkinterne Umspannplattform
Errichtung der parkinternen Umspannplattform
Errichterschiff Stanislav Yudin transportiert die Tripods
Errichtung der Tripods
Abtransport der Windkraftanlagen von Bremerhaven ins niederländische Eemshaven
Übergabe der AREVA Windkraftanlagen an Trianel
Blasenschleier bei den Rammarbeiten

Trianel Windpark Borkum

Chronology

 

September 2015

Commissioning and normal operation was established.

1 June 2014

The 40th turbine is installed - Trianel wind farm Borkum's first stage is completed.

March 2014

At the end of winter, 25 turbines are installed and 75 percent of cabling are completed.

27 July 2013

First turbine is fully installed.

July 2013

Installation vessel MPI Adventure starts with the installation of the 40 AREVA M5000 turbines.

April 2013

The converter platform is fully installed and ready for operation.

Februar 2013

The jacket of the converter platform is installed 

March 2012

Ramming works done. All 120 piles for the tripods are installed.

1 September 2011

Start of construction. First ramming action at sea.

June 2011

Preparations are made for the protection of sea mammals during the construction phase. A nozzle hose about 400 metres long and filled with compressed air is placed underwater around the pile at a distance of 60 to 70 metres. The nozzles are of different sizes, so that the bubbles vary in size. The rising bubbles form the sound protection wall. In collaboration with Hydrotechnik Lübeck GmbH, BioConsult GmbH & Co. KG in Husum and ITAB GmbH in Oldenburg, this sound protection technology will be tried and tested on a large scale during the construction of the Trianel Windpark Borkum.

Spring 2011

Preparations and design are on course for a building start in August 2011.

21 December 2010

Funding agreements are signed. 

15 December 2010

The Trianel Windpark Borkum partner’s meeting unanimously votes in favour of the project. 

5 May 2010

Trianel Windpark Borkum applies to TPS for network connection.

28 April 2010

A contract with Areva Multibrid for the supply of wind turbines is signed.

28 December 2009

Trianel offshore project receives over EUR 40 billion in EU subsidy funding. 

7 September 2009

Trianel enters a pre-contract arrangement to secure 40 No. M5000 AREVA Multibrid turbines. 

27 August 2009

Trianel GmbH has commissioned the private weather consultant EWC Weather Consult GmbH with the supply of intraday wind power prognoses.

13 May 2009

Trianel secures all rights to the Borkum West II offshore site. At the same time, the permission issued the previous summer by the Federal Maritime and Hydrographic Agency (BSH) to Prokon Nord Energiesysteme GmbH is acquired by Trianel.

January 2008

The Borkum West wind farm project gets an enthusiastic response from the partners; a project company is formed.